Work on the proposed construction or development shall begin within
180 days after the date of issuance and shall be completed within
12 months after the date of issuance of the permit or the permit shall
expire unless a time extension is granted, in writing, by the Floodplain
Administrator. The actual start of construction means either the first
placement of permanent construction of a structure on a site, such
as the pouring of slab or footings, the installation of piles, the
construction of columns, or any work beyond the stage of excavation;
or the placement of a manufactured home on a foundation. Permanent
construction does not include land preparation, such as clearing,
grading, and filling; nor does it include the installation of streets
and/or walkways; nor does it include excavation for a basement, footings,
piers, or foundations or the erection of temporary forms; nor does
it include the installation on the property of accessory buildings,
such as garages or sheds not occupied as dwelling units or not part
of the main structure. For a substantial improvement, the actual start
of construction means the first alteration of any wall, ceiling, floor,
or other structural part of a building, whether or not that alteration
affects the external dimensions of the building.